Construction management software for subcontractors

You win the job.We run your side of it.

It works out what you are owed, when you have to ask for it, and what happens if you are late. Then it writes the paperwork.

One account that runs the whole job: prestart, site, procurement, crew, claims, retention, handover. Never priced per user.

Four things that cost you, and what happens insteadFour jobs, three builders, one account, and it is yours
01You cannot get on site

Nothing was built today.

Six electricians turned up, the lift was on hire, the programme said level four fitout. The day did not stop because of the work.

Cost of the dayA$0A$1,920A$2,230A$2,400
6 electricians, stood down 4 hrsOwn crew. Paid whether the gate opens or not.CostA$1,920
Scissor lift, on hire, never movedDay rate runs from the moment it lands on site.CostA$310
Two utes out and back, nobody picked up a toolForty minutes each way, twice.CostA$170
Why the day stoppedCertificate of currency for public liability never lodged, and the subcontract still unexecuted. Refused at induction 06:39.MissingTwo documents
Crew not on siteHead contractor gate log / 06:39
YourCA / the Thursday before

Your insurances were ready to go to the builder before anyone drove out.

Public liability and workers compensation certificates pulled from your own records, checked against what the subcontract asks for, exported as one pack with the executed agreement for you to send.

You sent it to the builderFriday 8:02 am
Induction, MondaySix through at 06:38
Cost of the dayNil
02Paperwork after a ten hour day

The job finished at five.
You finished at ten.

The SWMS, the ITP results, the site diary, the photos. All of it written up hours after the work it describes, from memory, at the kitchen table.

Pen down10:25 pm5:02 pm
Your Tuesday now
6:30 am, start
5:00 pm, tools down
8:40 pm, kitchen tableDiary, ITP results, photos off the phone, tomorrow's work order
10:25 pm
Your Tuesday on YourCA
6:30 am, start
9:40, ITP signed at the hold point
12:35, photo and one line becomes a variation
2:20, diary written standing next to the work
5:02 pm, done

The record is made where the work is, on the phone, by whoever did it. Nobody types the day up twice.

ITPs with eleven response types, and nobody signs off their own work. Append only once signed.

03You get paid slow

The claim went in.
It came back cut.

Two variations struck out of a progress claim, for reasons you cannot argue with because the record that would answer them was never made.

Knocked back, then chasedA$23,760
The claim you servedClaimedTheir schedule
Work performed to the 25thFrom your schedule of ratesClaimedA$186,300ScheduledA$186,300
Variation 12, switchboard relocationTheir reason: no approval on recordClaimedA$14,820ScheduledA$0
Variation 14, core drillingTheir reason: notice out of timeClaimedA$8,940ScheduledA$0
Retention deductedClause 42.3, 10% to a 5% capClaimed−A$18,600Scheduled−A$18,600
Short paid, and chased for 34 daysWork already done, plant already hired, wages already paidClaimedA$191,460ScheduledA$167,700
YourCA / the day the work changed

The notice went in inside the window, so there is nothing to knock back.

A photo and one line in plain words became a priced variation off your rate card. The notice was drafted the same day, and it went out before the entitlement lapsed.

Variation 12Approval on record, dated
Variation 14Notice served day 2 of 5
Claim servedA$191,460, declaration attached

Reference date derived against the Security of Payment Act for the state you claim in. Every figure cites the clause or record it came from, and asks you when it cannot.

04Blind until the job is over

Retention from last year,
still sitting with a builder.

Retention comes off every progress claim and releases at practical completion and again at the end of defects liability. Two dates per job, on jobs you finished and stopped thinking about.

Retention held across finished jobsA$41,200
Finished jobHeldNext release
Fitout, western SydneyPractical completion 14 Mar last year. Nobody asked.HeldA$18,400Next release11 months late
Depot, MarrickvilleDefects liability ends 2 NovHeldA$14,600Next release2 Nov
Tower fitout, CBDFirst tranche at practical completionHeldA$8,200Next release9 Dec
Three finished jobs, two buildersHeldA$41,200Next releaseAll dated, all watched
YourCA / from the first progress claim

Ledgered as it is deducted, released on dates you did not have to remember.

Every deduction is recorded against the clause that took it, each tranche carries its own release date, and you are told a month out, a week out and on the day it falls due. Where you stand is a number you can read today, not one you find out at the final claim.

Across every job you have on: every notice window still open, who owes you and how old it is, ranked by what it costs you next.

Why this exists

Procore, Aconex, Payapps. All of it was built for the head contractor. This one was built for you.

So your side of the job runs off spreadsheets, a folder of PDFs and somebody else’s login. The builder’s record is kept for them, automatically. Yours is whatever you remembered to write down.

Their record of the jobYour record of the job
Access the builder can switch offAn account that belongs to you
Priced per seat, per officePriced per job, unlimited users
You get told after the dateYou get warned before it closes

You find out three days before, not three days late.

You will not miss a date again, and you will not have to remember one.

What is comingJobWhenWhere it stands
Claim dayRiverside Fitout · Lendlease3 daysClaim 7 assembled, ready to serve
Order the fixturesKent St Towers · BuilttodayOn site in 2 weeks, 3 week lead time
Variation 14 noticeKent St Towers · Built4 daysDrafted. Entitlement lapses day 5
Their payment scheduleRiverside Fitout · Lendlease2 daysWatching. Chased daily once late
Retention release, tranche 1Marrickville Depot · FDC30 daysA$18,400 falls due, ledgered
Public liability expiryAll jobs30 daysRenewal reminder, your records
Eleven kinds of reminder, worked out from your own contracts and your own records.4 jobs · 3 builders · one account: yours

From signed contract to served claim

Watch the work happen.

Step one · It reads the contractClause 42.1

“The Subcontractor shall give notice of any variation within 5 business days, failing which the entitlement shall lapse.”

Variation notice: 5 business daysHigh risk
Entitlement lapses if notice is late. YourCA warns 2 days before each clock shuts.
Claim day: 25th of the monthWatched
Reference date derived to the Act (NSW). Reminder lands 3 days out.
Retention: 10% to a 5% capLedgered
Deducted per payment to the cap, released in dated tranches.
Step two · The claim builds itselfServe 25 Aug
Work performed to 25 AugFrom your schedule of ratesA$186,300
Variation 12: switchboard relocationApproved 4 Aug, rate card pricedA$14,820
Variation 14: core drillingNotice served, clock runningA$8,940
Retention deductedClause 42.3, 10% to cap−A$18,600
Retention held to dateRelease 14 Mar 2027A$41,200
This claim, to the Act (NSW)A$191,460
Statutory declaration and Subcontractor’s Statement attached, on the NSW forms.

Every figure cites the clause or record it came from, and asks you when it cannot. Claims to the Security of Payment Act in NSW, QLD and VIC.

And the variation
A photo, and one line in plain words:
“They moved the switchboard.”
Variation 12 · A$14,820Priced from your rate card, notice drafted
  Notice window: 4 days leftBefore the entitlement lapses, not after.

Already paying for job management software?

Keep it. Then ask it three questions.

01

Does anything tell you the deadline to give notice on a variation, and show you the clause it came from?

02

Does your statutory declaration come out attached to the claim, on the right state form, before you serve it?

03

How much retention is out there right now across your finished jobs, and what date does each tranche release?

Every answer is no, and each one has already cost you. Your job software runs your business. YourCA runs your contract, beside it. Nothing to migrate.

Eleven modules. Three jobs to do.

Before you start
01ContractWhat can bite you

A risk register clause by clause, and every date it puts on you, watched from day one.

02PrestartThrough the gate

Your SWMS written from what you type, then statement, insurances and work order as one pack.

03DocumentsProving what you were told

Every version, with the day it arrived. Drawings marked with which revision you priced.

Running the work
04ProcurementNobody standing around

Order-by dates worked back from required on site. A chase drafted the morning an order slips.

05ScheduleWho is where tomorrow

Their programme becomes your dates. Crew clock on from their own phone, straight to the diary.

06SiteWhat stopped us today

ITPs with eleven response types. Nobody signs off their own work. Append only once signed.

Getting paid
07FinancialsDo not lose the variation

The claim assembles itself with the declaration attached. A photo and one line becomes a priced variation.

08HandoverThe tail that never ends

The O and M manual and close-out pack, built from the certifier’s own list.

09Calendar · Reports · DashAcross every job

Every notice window still open. Who owes you and how old. Ranked by what it costs you.

Set up in an afternoon, not a quarter.

01Add the jobOne project, one head contract. Drop the contract and drawings in, and their programme as CSV, XLSX or XER.
02We read itA risk register clause by clause, and every date the contract puts on you, each against the clause it came from.
03Run the workITPs, photos, diary, procurement and crew. The record accumulates while the job happens.
04Get paid, close outClaims assemble themselves, variations keep their entitlement, and the handover pack is built rather than chased.

Priced per job, not per person.

Free
A$0your first project, no card.
1 active projectEvery module, unlimited usersUnlimited storageOne contract review, once
Pay per job
A$249per job, per month. No commitment.
A$149 or A$249 a month per job, on its sizePay for the jobs you have onEvery module, unlimited usersUnlimited storage1 contract review a month per active job, then A$49 each
Five jobs
A$899per month, up to 5 active projects.
5 active projects includedThen A$149 or A$249 per extra job, on its sizeEvery module, unlimited users1 contract review a month per active job, then A$49 each
Unlimited
A$1,999per month, flat.
Unlimited projects and usersPriority supportOnboarding included1 contract review a month per active job, up to 15

The stood down day above cost A$2,400. A small job on the per-job rate is A$149 a month, A$1,788 for the year.

Every paid plan includes one contract review a month for each active job, up to 15 a month, then A$49 each. One review, once, on the free plan. Prices ex GST. GST is added at checkout and shown before you pay.

The ones subbies actually ask.

Straight answers, including the ones that cost us. If it needs signal to save, we say so.

Your first job is free. Start with the one giving you grief.

Put your worst head contract through it and see what it finds. No card, and nothing to migrate.

Sign up with your email address and a code arrives to sign you in. Your first job is free. Not a trial. The whole job, however long it runs, with unlimited people on your account.

Start free

No card. One active job on the free rung, and one contract review to prove it reads yours.

YourCA: construction software built for subcontractors